Introduction
Duplicating a Deployment Plan saves your time from re-entering information.
When a Master Deployment Plan is duplicated, its Systems and Releases are not duplicated because they are assigned in, and belong to, the child Deployment Plans.
When a Deployment Plan is duplicated, the Release value will not be duplicated and will be empty if that Release was at the End State Status.
The Duplicated Deployment Plans have their mode set to Draft.
The Audit History of the Deployment Plan is not duplicated, but the user performing the duplication will be marked as the creator of the plan in the new Audit History.
Pre-requisite
You must have the ‘Create Master Deployment Plan’ or the ‘Create Deployment Plan’ user permission.
Navigation
Deployment > Manager
Duplicate Deployment Plan
To duplicate a Deployment Plan:
- Go to Deployment > Manager.
- Select the checkbox of the Deployment Plan you would like to duplicate.
- Click
.
Duplicate Master Deployment Plan
For Master Deployment Plan fill in the following:
New Deployment Plan Name: Enter a new name for the duplicate Deployment Plan.
Items to Include in Duplicate:
Include items by selecting one or more of the following checkboxes. Items are grayed out if they do not exist in the Deployment Plan and therefore cannot be duplicated.
- Activities: Activity Sets are not duplicated. Set the Planned Start Time for the first Activity.
- Users select the day for the first Activity to start and Activities will cascade down from this selected date.
- For example, if there are three Activities each lasting two days, and the date selected is next Monday, the first Activity will start on Monday, the second on Wednesday, and the final one on Friday.
- If Users want to adjust times, they can do so by bulk updating the Activities in the Deployment Plan Activity tab.
- Activity Attachments
- Checkpoints: Set the Checkpoint Time for the first Checkpoint. Any following Checkpoint times will cascade down from the first Checkpoint.
- Issue Questions: Issue Answers are not duplicated because they are associated with the child Deployment Plan.
Click .
Duplicate Deployment Plan
For the Deployment Plan fill in the following:
New Deployment Plan Name: Enter a new name for the duplicate Deployment Plan.
Items to Include in Duplicate:
Include items by selecting one or more of the following checkboxes. Items are grayed out if they do not exist in the Deployment Plan and therefore cannot be duplicated.
- Activities: Activity Sets are not duplicated. Set the Planned Start Time for the first Activity.
- Users select the day for the first Activity to start and Activities will cascade down from this selected date.
- For example, if there are three Activities each lasting two days, and the date selected is next Monday, the first Activity will start on Monday, the second on Wednesday, and the final one on Friday.
- If Users want to adjust times, they can do so by bulk updating the Activities in the Deployment Plan Activity tab.
- Activity Attachments
Click .
The Deployment Plan will be duplicated and available on the grid.